In my last note I looked at GASTAT's Construction Cost Index. That index measures what contractors pay for their inputs. This note looks at the other side: what contractors are expected to charge.
JLL's revision
In its H1 2026 Saudi construction market review, published in October, JLL moved its 2026 tender price inflation forecast from 4% to around 5%, within a range of 4–6%. It expects about the same for 2027. The reasons it gives are metals and fuel: copper, aluminium and diesel all rose sharply over the year to August, and longer shipping routes added to landed costs and lead times.
Forecasts in this market move quickly. Earlier in 2026, JLL's outlook for Riyadh was around zero, somewhere between minus 2% and plus 2%. Anyone relying on a figure published even a few months ago should check whether it has since been revised.
What the other forecasters say
| Source | Measure | 2026 | 2027 |
|---|---|---|---|
| JLL (Oct 2026) | Tender prices | ~5% (4–6%) | ~5% (4–6%) |
| AECOM (Jan 2026) | Tender prices | 3–7% | – |
| AESG (Q2 2026) | Tender prices | 4–7% | – |
| Currie & Brown (Feb 2026) | Cost escalation | ~4% | – |
| RLB (2026) | Tender prices | – | – |
| Turner & Townsend (2026) | Cost inflation, Middle East | – | 5.1% |
| GASTAT CCI (Sep 2026) | Input costs, official | 2.2% y/y | – |
Two things stand out to me.
- Nobody is forecasting low single digits. The lowest point of any published 2026 range is AECOM's 3%. AESG's range, 4–7%, is based on tender returns from late 2025 to mid 2026, which makes it the most recent forecast built on actual bids.
- Tender prices are running ahead of input costs. The official index is around 2%. The tender price forecasts sit between 3% and 7%.
Why tender prices and input costs differ
An input-cost index measures what a contractor pays for materials, labour, plant hire and energy. A tender price index measures what the contractor charges, and that includes overheads, margin and an allowance for risk. When the market is busy, specialist trades are scarce and contractors are reluctant to take on fixed-price risk, tender prices tend to rise faster than inputs. When contractors are short of work, the opposite happens. Right now the forecasters are pointing to the first case: tight contractor capacity, shorter bid validity periods and higher risk allowances.
What this means for process plant
The caveat from my last note still applies. All of these are construction indices, weighted towards buildings and civils. For an oil and gas or petrochemical asset, they describe the local share of installed cost, not major equipment, alloy piping or specialist labour.
The comparison does add one point. A plant that has to be rebuilt after a loss isn't priced by input costs. It's priced by what contractors and vendors charge. That work is usually urgent and goes to a short list of qualified bidders, so a post-loss rebuild probably behaves more like a tender price index than an input-cost index, or worse. That's an inference, but it points the same way as the published forecasts.
My interpretation
For the local construction share of a Saudi asset, the published evidence for 2026–27 supports something in the range of about 3–6%. A figure below the official input-cost index would be hard to support from anything currently published. Imported equipment and bulks still need their own benchmarks. I'll update this note as the next round of reports comes out.