← Ghafoor Hussain

Saudi construction costs: what the latest index says, and what it doesn't

Annual growth in GASTAT's Construction Cost Index has gone from 0.7% to 2.2% in a year. But it is a buildings index, and for a process plant it covers only the local share of installed cost.

Subject
Cost escalation
Saudi Arabia
Published
November 2026
Revision
A
Reading
3 min

What the index shows

I've been tracking GASTAT's monthly Construction Cost Index (2023 = 100). Over the past year it shows a clear pickup in Saudi construction cost growth. Annual growth in the general index went from 0.7% in September 2025 to 2.2% in September 2026, after peaking at 2.7% in June.

What's driving it

The increase is not evenly spread.

  • Equipment hire with operator is up 5.9% on the year. Hire without an operator is up only 0.8%, so most of the increase is in operated, serviced hire rather than in the machines themselves. That may point to busy contractor fleets as much as to underlying cost. Most of the rise came in a single step in March 2026.
  • Basic materials have gone from falling (−0.3%) to rising (+1.7%). Rebar is up 4.3%, while structural steel sections are up only 1.0%.
  • Labour has been relatively steady at around 1.4–1.7%.
  • Energy is administered pricing and moves once a year, in January. Diesel accounts for most of that change.

The non-residential sector, the closest match to industrial work, rose 2.6% over the year.

Why this matters for process plant

The CCI is a buildings index. Its items are local construction inputs: cement, blocks, rebar, building trades and earthmoving plant. For an oil and gas or petrochemical asset, that covers only the local share of total installed cost: civils, steel erection, site labour and construction equipment. Depending on the plant, that's roughly a quarter to a third of the total.

The larger part of installed cost isn't in the index. That includes major equipment, alloy piping, valves, electrical gear, instrumentation and specialist labour. These are largely priced in global markets, often come from a small group of vendors, and carry long lead times. After a loss, they can also face competition for fabrication slots and construction crews from other major projects in the region.

My interpretation

If general construction costs are accelerating locally, it seems reasonable to expect that specialised process plant is under at least as much pressure. That is an inference rather than a measurement. The index can't confirm it, and the March step in equipment hire may prove to be a one-off.

For anyone escalating plant values in the Kingdom, I'd treat the local index as a floor for the local share of cost, not as a measure for the whole asset. Imported equipment and bulks need their own benchmarks.

Source: General Authority for Statistics (GASTAT), Construction Cost Index monthly releases, June 2025 – September 2026. Views my own.

Note 02 Rev A 2026 ghafoorhussain.com